Minimizing the total weighted late work in scheduling of identical parallel processors with communication delays

作者:Abasian Foroogh; Ranjbar Mohammad*; Salari Majid; Davari Morteza; Khatami Seyed Morteza
来源:Applied Mathematical Modelling, 2014, 38(15-16): 3975-3986.
DOI:10.1016/j.apm.2014.01.006

摘要

This paper addresses a certain type of scheduling problem that arises when a parallel computation is to be executed on a set of identical parallel processors. It is assumed that if two precedence-related tasks are processed on two different processors, due to the information transferring, there will be a task-dependent communication delay between them. For each task, a processing time, a due date and a weight is given while the goal is to minimize the total weighted late work. An integer linear mathematical programming model and a branch-and-bound algorithm have been developed for the proposed problem. Comparing the results obtained by the proposed branch-and-bound algorithm with those obtained by CPLEX, indicates the effectiveness of the method.

  • 出版日期2014-8-1