摘要

This research examined the use of a single facultative pond for treatment of an intermittent discharge from a UK campsite. The system was monitored over an 11-month period to determine the optimum time for discharge in terms of quality standards. The results showed that based on organic strength, discharge was possible in winter between November and March but February was the optimum to meet nutrient and suspended solids requirements. The pond showed rapid acclimatisation to the influent wastewater, with biochemical oxygen demand removal rates during the filling period of around 60 kg ha(-1) day(-1) and removal efficiencies of similar to 95% after maturation. The system proved simple to operate. A major design factor is the requirement for storage of net incoming precipitation, which may provide dilution of residual pollutants but requires additional system capacity.

  • 出版日期2012