摘要

This paper considers a single machine scheduling with both deterioration and positional effects and due-window assignment problem. The job-dependent due-windows are obtained by the common flow allowance criterion. The objective is to schedule the jobs, and the due-windows so as to minimize the sum of earliness, tardiness, and due-window starting time and due-window size costs. We introduce a polynomial solution for the problem. Furthermore, we show how the solutions can be extended to the setting with job rejection.